Dannebrog Remodel


 

2026 Web Banners.png
 

2026 Web Banners (1201 x 250 px).png


12_24_2025.png

Construction prep has commenced! The back storage room addition was also removed.

12_24_2025.png
 

12_29_2025.png

Interior prep continues! Walls were built and windows covered to separate the south side from the north side of the building.

12_29_2025.png
 

12_30_2025.png

The first phase of construction includes removing all of the interior walls and ceiling on the south side of the building.

12_30_2025.png
 

12_31_2025.png

We wrapped up the year by uncovering a few beautiful design features from the past -- check out that original brick interior wall and tile ceiling!!

12_31_2025.png
 

1_9_2026.png


The drop ceiling is officially down. Now we can see more of the beautiful original tile ceiling!

1_9_2026.png
 

1_12_2026.png


All of the interior walls of the south side have been removed. One of the biggest updates of the building will include raising the south side of the building to be level with the north side!

1_12_2026.png

 

1_15_2026.png


The crew is working on clean up of the south side along with removing the night drop and ATM to make room for raising the floor on the south side. When all is said and done, the south side and north side will be all the same level!

1_15_2026.png

 

1_21_2026.png


Whew! That ole night drop was difficult to yank out! The crew is still working on the south side, clearing everything out in preparation for raising the floor.

1_21_2026.png

 

1_28_2026.png


Subfloor = INSTALLED! Interior walls = GOING UP!

We are making FAST progress on the south side of the building where the future offices, breakroom, and lobby will be.

1_28_2026.png
 

2_2_2026.png


Oh my! How beautiful is this arched doorway between the south and north sides of the building?!?! This is where our members and visitors will move from the front door, lobby sitting area, and offices to the teller line.  One of our highest priorities with this building remodel is to harken back to the way the original bank building looked. This arched doorway is key to that design vision. In addition, the crew is making quick progress on the rest of the office walls on the south side.

2_2_2026b.png

2_2_2026.png
 

 

2_18_2026.png



We're getting ready to move into the finish stages for the south side!

2_18_2026.png
 

2_24_2026.png




We'll be retaining that beautiful original ceiling tiles wherever we can. Drywall is also going up in the lobby area and offices.

2_24_2026.png
 

2_24_2026 (2).png
 

 

2_27_2026.png




Still working on the walls and ceiling on the south side. The nice weather is also allowing more work to continue on the backside of the building.

2_27_2026.png
 

2_27_2026 (2).png
 

 

3_3_2026.png




Just wait until you see what we have planned for the lobby area on the south side. There's a couple of hints in these photos...

3_3_2026.png
 

 

3_4_2026.png




Since we raised the subfloor on the south side, we're also raising the sidewalk leading up to the door. Out with the old . . .

3_4_2026.png
 

 

3_5_2026.png




. . . and in with the new!

3_5_2026.png
 

 

3_11_2026.png




Prepping the walls and ceiling for a fresh coat of paint. Also installing the HVAC and lighting needed to each of the offices.

3_11_2026.png
 

3_11_2026 (2).png
 

 

3_12_2026.png




Primer is up on those ceiling tiles!

3_12_2026.png

 

 

3_17_2026.png





And base coat up on the interior walls!

3_17_2026.png
 

 

3_20_2026.png



Bringing new life to those tiles. This color will go perfectly with our redesign which calls back to this building's history.

3_20_2026.png
 

 

3_23_2026.png



Installing the drop ceilings in each of the offices today.

3_23_2026.png
 

 

3_25_2026.png



More drop ceiling work on the south side today.

3_25_2026.png
 

 

3_31_2026.png




Ohhhh! Ahhhh!! We weren't able to keep any original interior brick work, so we went with the second-best option.

3_31_2026.png
 

 

4_6_2026.png




Just look at the color of the bricks and trimwork with that new ceiling color!

4_6_2026.png
 

 

4_7_2026.png



More trimwork and some much-needed upgrades to our staff breakroom are being installed today.

Oh, and how about a fireplace for the lobby?!

4_7_2026.png
 

 

492026.png


Gah! Look at this lobby!! Is it just us or is choosing proper light fixtures an underrated statement in interior design?!


4_9_2026.png
 

4_9_2026 (2).png
 

 

4202026.png


More new surfaces are surfacing! Check out the beautiful new carpet in the lobby and office hallway as well as flooring and tiles in the public bathroom.

4202026 (1).png